United KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomPolandPolandBelgiumSwedenSwedenSwedenSwedenSwedenNetherlandsNetherlandsSloveniaTurkeyTurkeyPortugalPortugalPortugalPortugalPortugalGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceSpainSpainSpainSpainSpainSpainSpainSpainSpainSpainSpainSpainSpainBulgariaItalyItalyItalyItalyItalyCzech RepublicSlovakiaGermanyGermanyGermanyGermanyAustriaFranceFranceFranceFranceFranceFranceFrance

Legend

 
smart
 
fair
 
improvable
 
troublesome
 
bad
Severe barrier

Database Help

PV FINANCING is a follow-up project of
PV Grid
Last update: 30.03.2017

National Contact Point: eclareon GmbH - Stefan Ćetković
(pt1(at)eclareon.com)

Small rooftop systems on residential buildings up to 10 kWp in size made up 18% of the German PV market in 2013. Whether a PV system requires a planning permission is being regulated by the states’ building regulations and thus might vary from state to state depending on the purpose of use, size, etc. For this reason, contacting the relevant building control authority before installing the PV system is recommended.The installation of a PV system can also be a ... (Unhide text)
 
Small Rooftop PV System on private residential buildings.
On-site meeting/proposal from the installer
Business Models
Credit under the programme Renewable Energies “Standard” of the government-owned development bank ...
Regional grants (no broad-range support)
Contacting the local building authority
Information to neighbours
Building permission procedure
Permission of the Monument Protection Authority
Grid connection application
Allocation of the connection point
(where required) Grid optimisation, upgrade and expansion
Connection proposal of the grid operator
Grid connection agreement conclusion (optional)
Agreement on the installation and purchase of the turnkey system
Installation of the PV system
Date of the commissioning of the system
Duty to register with the Federal Network Agency and entitlement to support
Feed-in agreement (optional)
Feed -in management
Notification of a business activity with the tax authorities/VAT
Examination of the income tax duty
Notification of a business with the labour inspectorate/business tax
Date of commissioning of the system
Connection of the system and commissioning
Commissioning protocol
Installing and operating the measuring facilities
Insurance of a PV system
Event of loss
Service, cleaning and reading the meter
Exchange of modules