United KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomPolandPolandBelgiumSwedenSwedenSwedenSwedenSwedenNetherlandsNetherlandsSloveniaTurkeyTurkeyPortugalPortugalPortugalPortugalPortugalGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceSpainSpainSpainSpainSpainSpainSpainSpainSpainSpainSpainSpainSpainBulgariaItalyItalyItalyItalyItalyCzech RepublicSlovakiaGermanyGermanyGermanyGermanyAustriaFranceFranceFranceFranceFranceFranceFrance

Legend

 
smart
 
fair
 
improvable
 
troublesome
 
bad
Severe barrier

Database Help

PV FINANCING is a follow-up project of
PV Grid
Last update: 31.05.2017

National Contact Point: eclareon - Ivana Naydenova
(in(at)eclareon.com)

The sector of small rooftop systems on residential buildings in Slovenia has developed rapidly in the years 2010-2012. Changes in the support mechanism in late 2012 (lower/regressive feed-in prices) and 2015 (introduction of a tendering procedure) led to an almost complete stop in terms of investments into the PV industry. The tendering process was not opened untill late 2016. Due to current tender criteria in the support ... (Unhide text)
 
Rooftop PV systems on residential buildings fall under the general legislation for RES Systems up to 1 MWp (simple devices).
Acquire the Location information
Check the suitability of the roof
Check the suitability of the electric cable entry
Check the roof ownership
Request for the project plan conditions
Prepare a detailed plan (PZI)
Apply for a preliminary Grid Connection Permit
Credit with a bank or Eco Fund
Business registration
Installation / Construction
Construction Check-up
Technical Check-up
Negotiate a Grid Connection Agreement
Presentation of documents
Take additional measurements
Additional demands
Sign the Grid Connection Agreement
Obtain the Declaration for the production unit
Sign into the business register (AJPES) and open an account at the Energy Agency
Compete on the tender
Sign the agreement
Maintenance of the PV installation
Security measures requirements
Telemetry of the electric flow
Transmission of certificates of origin